Homebuyers who discover that a promoter has breached the (BBA), deviated from , or violated often face a practical dilemma: should the complaint be filed before the RERA Authority or before the Adjudicating Officer? of the , permits an to approach either forum, but the correct choice can determine whether the complaint survives at first hearing. Understanding the statutory division of functions between these two bodies is essential before initiating proceedings.
The Short Answer: Approach the RERA Authority First
A complaint alleging violation of BBA terms and zonal plans should generally be filed before the , not the Adjudicating Officer. The Authority is the primary forum empowered to determine breaches of the Act, the rules, and the regulations. Only after the Authority has found a breach may the question of be referred to the Adjudicating Officer under .
This division of labour is not merely procedural. Courts have repeatedly cautioned that when an Adjudicating Officer assumes the role of the Authority, it exceeds its jurisdiction and its orders may be quashed 2023 0 Supreme(Guj) 371 and 2021 0 Supreme(Bom) 804.
Why the Authority Holds the Primary Jurisdiction
The Authority enjoys wide-ranging statutory powers covering the full spectrum of violations:
- empowers RERA to investigate complaints 2025 Supreme(Online)(Bom) 4223.
- empowers RERA to issue interim orders in the context of any contravention — essentially a remedial power 2025 Supreme(Online)(Bom) 4223.
- confers the power to issue directions in implementation of the Act 2025 Supreme(Online)(Bom) 4223.
- empowers the Authority to impose penalties or interest upon contravention of the Act and subordinate legislation 2025 Supreme(Online)(Bom) 4223.
(1) expressly provides that any may file a complaint with the Authority or the adjudicating officer, as the case may be, for any violation or contravention of the provisions of the Act or the rules and regulations made thereunder, against any promoter, , or real estate agent 2025 0 Supreme(P&H) 12 and 2025 0 Supreme(P&H) 1002. In the case of sanctioned building plans and layout deviations, the Authority is the body equipped to investigate and direct remedial action 2025 0 Supreme(P&H) 1002 and 2026 Supreme(Online)(Gau) 6987.
The Adjudicating Officer's Narrow Mandate: Only
The Adjudicating Officer, appointed under (1), exists for one specific purpose — adjudging under of the Act 2003 0 Supreme(Bom) 1358 and 2021 0 Supreme(Bom) 804. Key features of this limited role include:
- The Authority decides all questions of breach of the Act, Rules, and Regulations, and then refers the question to an Adjudicating Officer on its panel, who decides the matter preferably within 60 days 2021 8 Supreme 15.
- These provisions do not impose any liability on the to pay , nor do they confer any right on the promoter to claim from an 1974 0 Supreme(SC) 388.
- The power exercised by the Adjudicating Officer is — it cannot be exercised by any member or officer of the Authority under 2021 8 Supreme 15.
Judicial decisions have enforced this boundary strictly. In one matter, the court held that the Adjudicating Officer exceeded its jurisdiction by assuming the Authority's role of restoring possession, since only the Authority could pass such orders under the complaint procedure in Form-A 2023 0 Supreme(Guj) 371. Similarly, where an Adjudicating Officer entertained a complaint concerning a project that did not require registration, the High Court quashed the order, reaffirming that registration determinations lie solely with the Authority 2021 0 Supreme(Bom) 804.
Refund Versus : Two Distinct Claims
The Act treats and as two distinct components that an aggrieved may claim, each with its own enquiry and mechanism under the Act 2021 8 Supreme 15. Refund and breach-related directions are matters for the Authority, while monetary for loss flows through the Adjudicating Officer once the breach is established.
Notably, also permits a complainant to withdraw a complaint pending before the Authority and refile it before the Adjudicating Officer in matters governed by — an option, though not the default route 2021 0 Supreme(SC) 23.
The Bar on Civil Court Jurisdiction
Reinforcing the RERA mechanism as the proper forum, bars civil courts from entertaining suits where the Authority or Tribunal can determine the issue 2025 Supreme(Online)(Bom) 6175. Where disputes involve complex questions of fact and law — such as contested BBAs — High Courts typically direct parties to pursue the statutory appellate route before the rather than invoking writ jurisdiction A) - Section 18 and Section 43(5).
Practical Limitations to Keep in Mind
- For unregistered projects incapable of registration under , the RERA framework may not apply, and remedies may lie outside RERA 2024 0 Supreme(Bom) 1089.
- Complaints by persons who are not allottees, promoters, real estate agents, or registered voluntary consumer associations may fall outside 's scope — for instance, landowners have been held not to be allottees under 2026 0 Supreme(Bom) 427 and 2026 Supreme(Online)(Gau) 6987.
- Non-registration of a project by the promoter does not, by itself, defeat an 's complaint; the Authority retains jurisdiction 2025 0 Supreme(P&H) 12.
Recommended Course of Action
- File first before the RERA Authority, framing the complaint under and alleging violations of the Act's provisions, including BBA breaches and zonal/sanctioned plan deviations.
- Do not file directly before the Adjudicating Officer for breach determination; the Authority must first find the violation.
- Seek through referral — once the Authority finds a breach, it will refer the claim to the Adjudicating Officer under 2021 8 Supreme 15.
- Ensure the complainant qualifies as an — typically an , promoter, real estate agent, or registered consumer association 2026 0 Supreme(Bom) 427.
Key Takeaways
The scheme of the RERA Act creates a two-tier adjudicatory structure: the Authority decides breaches of the Act, Rules, Regulations, BBAs, and zonal/sanctioned plan violations, while the Adjudicating Officer's jurisdiction is confined to under . Blurring this line can render an order vulnerable to being quashed. Filing the BBA and zonal plan complaint before the RERA Authority in the first instance is therefore the generally correct and strategically sound approach. This article reflects general legal information based on statutory provisions and precedents and should not be treated as advice for any specific matter.